Transtech Scope of Work: Program Manager,
Construction Manager
Project: Transtech was retained by the City to take over the management
of this multi million dollar facility which was 2 years behind schedule.
Within 5 months, Transtech brought the construction to substantial
completion level allowing the City start the move-in process, and
2 months after, the facility was opened to public use.
Total Project Cost: $25,000,000
|